Work on a major Adani Green Energy hydropower project in Maharashtra has been ordered to stop after the state Forest Department said construction began without required approval from the National Board for Wildlife. The project is the 1500 megawatt Tarali Pumped Storage Project in Patan taluka of Satara district.

The department issued the stop work direction on November 13 and asked the company to explain why work started without the wildlife approval. It also sought copies of statutory permissions and documents related to tree cutting. The department warned that legal action could follow if the company failed to provide a satisfactory reply. The project has also come under attention because of a sharp change in its reported cost. Its environmental clearance had listed the project cost at Rs 5675 crore. In a later affidavit, the company stated a cost of Rs 56.75 crore. As a result, the wildlife conservation deposit linked to the project fell from Rs 227 crore to about Rs 2.27 crore. The money is meant for conservation work connected with the Sahyadri Tiger Reserve.

The Union Environment Ministry has directed the state to investigate the matter on priority. Adani Green Energy has disputed the allegation of starting work without required permissions. The company says it has obtained environmental and other clearances, and that its wildlife approval proposal is being considered. The project will remain on hold until the required approval issue is resolved.